This renovation and new construction project required intensive preconstruction services due to the sloping, rocky terrain and tight site restrictions not normally seen on an urban campus setting. The project entailed the renovation of four floors and seven levels of stacks and also
included a new 45,000-SF addition to the library. On a 205'
x 80' site, pinched between the existing library the college’s
main cafeteria and steam plant, our firm constructed the
new library addition. Site limitations also included a main
construction access point that was shared with the many
delivery trucks going to and from the cafeteria and steam
generation plant.
The existing library dates back to 1937, the new addition
ties in to the existing structure and required the matching
of floor plates to allow windows of the old structure to
become doorways into the new addition. The foundation of
the addition bears on rock, and the fully finished basement
was constructed as a slab on-grade, requiring soil retention,
rock anchoring and sheeting on three sides to hold back
the hillside. To resolve the sloping site topography, the
first floor was constructed on a concrete framed slab with
the balance of the building composed of structural steel.
The first floor concrete framing tied into the foundation
walls of the existing library, creating a frame that resists
the unbalanced earth loads placed on the structure due to
the sloping site.
A crane rested on the first floor concrete slab while the
balance of the building's frame was erected. The crane's
positioning on the first floor elevated slab required heavy
shoring extending from the underside of the first floor
slab to the basement level slab. The site restrictions came
into play during steel erection and prevented the construction
of the building in a conventional manner. Instead of erecting
the structure upward, floor-by-floor; floors 2-4 were erected
to their full height at one end of the building, and then
the process was repeated moving horizontally across the
building, bay-by-bay. This was the best choice of construction
to allow for complete access to the surrounding buildings
by students and staff.
The main level of the library is at the third level and
is accessed by a precast bridge. The exterior of the building
is brick and EIFS with glass curtainwall. |